PROJECTED FIELD SCHEDULE
2009/2010 Field Season
  • Continue deep drilling with DISC Drill

    2010/2011 Field Season
  • Continue deep drilling with DISC Drill. Stop drilling 50 to 30 m above bed.
  • (Possible) Borehole logging (January)

    2011/2012 Field Season
  • Borehole logging (Nov and Dec)
  • Replicate coring (Jan)

    2012/2013 Field Season
  • Replicate coring (Nov-Jan)

    2013/2014 Field Season
  • Retrograde DISC Drill

  • FIELD ACTIVITIES ALREADY COMPLETED
    2008/2009 Field Season
  • Continue deep drilling with DISC Drill (brittle ice)

    2007/2008 Field Season
  • Finish arch construction
  • Install DISC Drill
  • Install core handling/processing equipment
  • Begin deep drilling with DISC Drill

    2006/2007 Field Season
  • Began interior arch construction activities
  • Drilled 130 meter ice core outside of arch facility
  • Drilled and cased 100 meter pilot hole inside arch facility
  • Installed two DISC Drill gantry cranes inside arch

    2005/2006 Field Season
  • Establishment of seasonal field camp at WAIS Divide
  • Began construction and assembly of drilling and core handling/processing arch facility
  • Drilled several shallow ice cores

  • Last Updated: April 2009